County Road 10: Buffalo Regrade and Asphalt Surfacing
One of the largest projects this year is the County Road 10 reconstruction and paving project through Buffalo.
Construction in Buffalo is progressing through a three-phase approach designed to maintain local access while improving the roadway and drainage system. Crews have completed removals and are currently installing storm sewer infrastructure. Curb and gutter work will begin soon, followed by aggregate base placement.
The project includes improved drainage, a wider roadway through town, upgraded sidewalks, and paved parking areas. Outside the Buffalo business district, County Road 10 will receive a new asphalt surface between Tower City and Buffalo. The roadway will be paved 36 feet wide with six inches of asphalt.
Phase One is expected to be completed by mid-July, Phase Two by late August, and Phase Three by mid-October. Asphalt paving is anticipated to begin in late July and continue for approximately four weeks.