The North Dakota Department of Transportation (NDDOT) and the City of Fargo contractors announce that the underground utility and roadway construction portions of the Phase 2 - 52nd Avenue S Roadway Reconstruction project will begin on Monday, July 1st, 2024, and is anticipated to conclude August 15th, 2024. This closure of the 52nd Ave S and Sheyenne Street roundabout will be in addition to the ongoing work in Phase 1 east of the Sheyenne River and up to 63rd St S.
Work for all phases remains scheduled to be complete by late August 2024.
Pedestrian access is not currently supported through this corridor, so no pedestrian access will be maintained.
The City of Fargo appreciates the public's cooperation and patience during the construction period. Please plan your routes accordingly and drive safely in construction zones.